Santa Anita Canyon Road Repair

Project No. C-3007

From the City of Monrovia, California…

NOTICE TO RESIDENTS & BUSINESS OWNERS

The City of Monrovia’s Public Works Department awarded a contract to D.J. SCHEFFLER, INC. to do the street repair at two (2) locations along Santa Anita Canyon Road. On December 10, 2012 we will start construction of the above project.

Anticipated completion date: April 2013.

The general scope of work includes excavation, drilling of pile shafts, installation of soldier piles and wood logging, grading, asphalt removal and replacement, drainage and street striping.

We understand that this construction project will impact residents and businesses in your neighborhood; we want to assure you that we will do everything possible to minimize this impact.

During construction one lane of the roadway will remain open, we will make every effort to maintain access to and from Chantry Flats property at all times, including emergencies, providing flagmen to assist us during construction activities.

Our work hours are from Monday to Friday from 7:00 a.m. to 5:00 p.m., and no construction is anticipated during weekends.

For your safety, please observe and comply with all posted construction and traffic signs. The street will be open for traffic at the end of each work day, or whenever construction work is not in progress.

Please send the City of Monrovia’s Public Works Department an email at pwcomments@ci.monrovia.ca.us or leave a voice message at (626) 932-5574 should you have any questions regarding this project. We will address your concerns promptly.

We apologize for the inconvenience during this process.

Thank you for your cooperation and assistance.

(link to Monrovia site)

Construction Schedule Update:

We were told by the contractor that the road will be closed Monday, Feb 25 from 9 am – 12 noon.

Chantry Road Closed on Monday, February 25
The contractor will be bring up a skip-loader on a over-sized trailer on Monday. They cannot be on the roads until after 9 am and so will be on the Chantry road after that. The road will be closed until they can get up, unload, and get back down. Plan for 9 to 12. Don’t get stuck up the hill.

Mon, Feb 4 through Fri, Feb 8 2013 – Drilling piles at southern area. Intermittent lane closure only as necessary for few minutes at a time. One lane of the roadway will remain open.

Monday, January 14, 2013 – No work scheduled.

Tuesday, January 15, 2013 – No work scheduled.

Wednesday, January 16, 2013 – Mobilize using intermittent traffic control for miscellaneous equipment and materials;  intermittent  lane closure only as necessary for few minutes at a time. One lane of the roadway will remain open.

Thursday January 17, 2013- Mobilize using intermittent traffic control for miscellaneous equipment and materials;  intermittent  lane closure only as necessary for few minutes at a time. One lane of the roadway will remain open.

Friday January 18, 2013- Mobilize using intermittent traffic control for miscellaneous equipment and materials;  intermittent  lane closure only as necessary for few minutes at a time. One lane of the roadway will remain open.

Mon. – January 21, 2013- Martin Luther King Holiday. No work scheduled.

Tues. – January 22, 2013- Mobilize misc. equipment. Installation of ¾” all-thread rods through the existing fieldstone wall at southern pile locations. Intermittent lane closure only as necessary for few minutes at a time. One lane of the roadway will remain open.

Wed. – January 23, 2013- Mobilize misc. equipment. Installation of ¾” all-thread rods through the existing fieldstone wall at southern pile locations. Intermittent lane closure only as necessary for few minutes at a time. One lane of the roadway will remain open.

Thur. – January 24, 2013- Mobilize misc. equipment. Installation of ¾” all-thread rods through the existing fieldstone wall at southern pile locations. Intermittent lane closure only as necessary for few minutes at a time. One lane of the roadway will remain open.

Fri.     – January 25, 2013- Mobilize misc. equipment. Installation of ¾” all-thread rods through the existing fieldstone wall at southern pile locations. Intermittent lane closure only as necessary for few minutes at a time. One lane of the roadway will remain open.

Note: Construction Schedule is subject to change depending on the actual field condition.